Hydropower Plant Investment Opportunity in Jammu and Kashmir, India

We are into renewable energy and IT, we are executing turnkey projects and on boot.
This transaction has concluded.

Established 10-20 year(s)
Employees 10 - 50
Legal Entity Private Limited Company
Reported Sales USD 1.45 million
Run Rate Sales USD 1.56 million
EBITDA Margin 10 %
Industries Engineering, Procurement & Construction + 1 more
Locations  Jammu and Kashmir
Local Time 10:17 PM Asia / Kolkata
Listed By Business Owner / Director
Status Moderately Active
Overall Rating
Partial Stake Sale
USD 5.8 million for 40.0% stake (Native Currency: INR 500,000,000)
Reason: We require funds to expand our business into hydropower and complete the 2 remaining projects and sc... View More
Includes physical assets worth USD 8.4 million
Interested to connect with advisors
Documents
Business Overview
- 13-year-old EPC company with a history of successful and delivered EPC projects.
- Company has successfully delivered 10+ EPC projects.
- Our company has been earned revenue in the past through EPC and various other projects. Currently we are having projects in IT and Hydro power to the tune 100 crore.
- Company has been allotted 3 small hydropower projects in the IPP (Independent Power Producers) mode.
- Our first, 6 MW (actually 7.2 MW with reserve) hydropower plant is near completion and will be commissioned in the next 3 months.
- PPA is done and the envisaged energy generation from this plant alone is around 32 million units.
- There are two more projects of 7 MW each that for which detailed Engineering is going on and work will be started after we get the survey and design.
- The investor will get a stake in this company.
- We require funds to complete the 2 remaining projects and want to bid for more projects both on EPC and boot basis. Our goal is to become national player in Hydro power and IT business.
Products & Services Overview
Construction of substations, civil works for power projects, hydropower plants.
Assets Overview
The market thumb rule of a hydropower project valuation is INR 10 crore/MW, which takes our 7.2 MW project's value to INR 72 crore.
The project has 3 hectares of land which has been allotted to us for the next 40 years.
Facilities Overview
Company headquarters are located in J&K.
3 hectares of land has been allotted to us for 40 years for the 6 MW (7.2 MW) project. Office in Srinagar with built up area of 30,000sqft.
Capitalization Overview
Not Disclosed
Recent Activity
Disclaimer: SMERGERS is a regulated marketplace for connecting business sell sides with investors, buyers, lenders and advisors. Neither SMERGERS represents nor guarantees that the information mentioned above is complete or correct. Note that SMERGERS is not liable for any loss, damage, costs, claims and expenses whatsoever arising from transacting with any other user from the website. The final responsibility of conducting a thorough due diligence and taking the transaction forward lies with the users. Please read best practices on SMERGERS.
This transaction has concluded. View similar business opportunities on SMERGERS
Disclaimer: SMERGERS is a regulated marketplace for connecting business sell sides with investors, buyers, lenders and advisors. Neither SMERGERS represents nor guarantees that the information mentioned above is complete or correct.
Frequently
Asked
Questions
  • Why can’t I see the business’ name or contact number? How do I contact the business?
  • What level of due diligence does SMERGERS conduct on the businesses/member?
  • How active are the business profiles listed on SMERGERS?
  • How does SMERGERS rate business profiles?
  • Do I need to pay to connect with a business?
  • Show more